Difference between practical completion and partial possession
The extent to which building works have been completed and whether a client can occupy a building or not is an issue that often arises during a project. There can be pressure to occupy a building, even if the works are not complete, and this can lead to disputes if the differences in the options available are not properly understood.
[edit] Practical completion
The contract administrator certifies practical completion when all the works described in the contract have been carried out. This is when, leaving aside minor items and/or snagging, the works are considered to be complete.
Once the certificate of practical completion has been issued, the client takes possession of the works for occupation. At this point the contractor no longer has exclusive possession of the site, and their obligation to insure the works and their liability for liquidated damages for delay comes to an end. Depending on the type of contract, at this point the contractor usually becomes entitled to half of the retention monies.
Practical completion signifies the beginning of the defects liability period, during which the contractor must make good any defects that become apparent. It is important to note that the defects liability period is not a chance to correct problems apparent at practical completion, it is the period during which the contractor may be recalled to rectify defects which appear following practical completion. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
[edit] Partial possession
The client may wish to take possession of part of a building or site, even if works are ongoing. This can be programmed within the original contract documents it the need can be foreseen through a requirement for sectional completion, but in the absence of such a provision many contracts offer the more open-ended option of partial possession.
The effect of partial possession is that:
- Any part for which partial possession is given is deemed to have achieved practical completion.
- Half of the retention for that part must be released.
- The defects liability period begins for that part.
- Liquidated damages reduce proportionally.
- The client is responsible for that part and should insure it.
The contractor is not obliged to allow partial possession (although permission cannot be unreasonably withheld), and may not wish to if, for example, access routes are difficult to achieve, it would disrupt the works, or it would incur additional costs. There could also be additional difficulties if the occupants of the part that has been possessed disrupt the contractor, which could result in a claim for extension of time and/or loss and expense.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments
under JCT D&B 2016, if partial possession is agreed and partial possession certificates are issued for all areas of works individually, does one still need to issue a practical completion certificate at the end of the project?